The Paradip Port Authority (PPA) invited bids for undertaking maintenance dredging of approach channel, entrance channel, turning circles and docks at Paradip Port for the year 2026-27 on December 10, 2025. The last date for bid submission is January 27, 2026.
The work is expected to be completed in six months at an estimated cost of Rs 1,228 million.
The project involves dredging of 4.14 mcum quantity from approach channel, entrance channel, turning circles and docks of Paradip Port for the year 2026-27. It is expected to be completed by October 31, 2026.